| 2024-07-23 | BP2023-21813 | Final | All Directives | Acceptable | No deficiencies noted. No further building inspections are required. - Ok to proceed. No further building inspection required. |
| 2024-07-18 | BP2023-21813 | Final | All Directives | Not Acceptable | Mechanical compliance is required prior to occupancy. - MP2024-02715 to be closed before occupancy. |
| 2024-07-18 | BP2023-21813 | Final | All Directives | Not Acceptable | Correct noted deficiencies and recall building inspection. - Call for inspection when MP is complete. On site inspection not required at next process. |
| 2022-06-28 | BP2022-09345 | Final | General Inspection Observations | Acceptable | New fire alarm panel installed. New door pull station installed. Visual devices installed. |
| 2022-06-28 | BP2022-09345 | Final | Field Level Hazard Assessment (FLHA) | Acceptable | Field Level Hazard Assessment: Conditions were sunny. Handrails, Guards in place. No unsafe conditions identified. Hard hat, Safety boots and vest worn. |
| 2022-06-06 | BP2021-19198 | Final | General Inspection Observations | Acceptable | Tenant Improvement Inspections Observations were: - Trade permits complete. Close file. |
| 2022-05-12 | BP2021-19198 | Final | Documents Commercial | Acceptable Add Inspection | contractor is to ensure that all trade Permits are closed prior to calling for Final. |
| 2022-05-12 | BP2021-19198 | Final | General Inspection Observations | Acceptable Add Inspection | received File documents, Final C1and 2 schedule to be submitted when work completed. |
| 2022-05-10 | BP2021-19198 | Final | General Inspection Observations | Acceptable Add Inspection | Tenant Improvement Inspections Observations were: work completed except for the exhaust duct for the 3D printing room and spray booth room which is still being worked on, the Mechanical Permit is still open as a result. the duct will be run vertically through the adjacent exit as previously noted, the duct will not imp |
| 2022-04-27 | BP2021-19198 | Final | Exiting | Acceptable Add Inspection | As Noted in NBC(AE)2019 3.4.4.4, nothing can be in an Exit which is not either dedicated to the Exit or Sprinkler Lines. Other ducts, piping or services may be run in the Exit, Other services may be run in the space, if there is room in the Exit, as long as they are encased in a Rated Assembly, a Shaftwall or wrap whic |
| 2022-04-14 | BP2021-19198 | Progress | Directives | Acceptable with Conditions | Call 311 to book an inspection For a building final. The building final should only be called once all the deficiencies completed , trade permits closed ( proof that all trade permits are completed), and All the required documents are available on site for the Building SCO to have for the file. |
| 2022-03-17 | BP2021-19198 | Progress | Fire Stopping | Acceptable with Conditions | Firestopping of the penetrations through the slab, to be provided on site for the final. |
| 2022-03-17 | BP2021-19198 | Progress | Emergency Lighting and Exit Signs | Acceptable with Conditions | *3.4.5.1. Exit sign to be visible on approach to the exit |
| 2022-03-17 | BP2021-19198 | Progress | Fire Resistance & Fire Separations Part 3 | Acceptable with Conditions | 3.1.9 Service penetration, seal by firestop system for the penetrations into the building shafts. |